California readies itself for a summer without San Onofre nuclear plant

Sponsored by

Progress is being made on more than a half-dozen upgrades to the transmission system in Southern California that are intended to help address supply adequacy issues that could result from Southern California Edison’s (SCE) June 7 decision not to reopen the San Onofre Nuclear Generating Station (SONGS).

On the heels of SCE’s announcement, officials with the California ISO (Cal-ISO) made the prediction that the state as a whole would be in “reasonably good shape this summer, even without SONGS'” 2,200 MW of generating capacity, except in southern Orange County and in San Diego, where Cal-ISO expected transmission constraints to result in challenges to importing the power needed.

The projects, many of which are aimed at alleviating those constraints, were presented to the ISO’s board of governors in February and have either been completed or are nearing completion by the various companies and utilities involved.

Projects include the conversion of Huntington Beach generating units 3 and 4 into synchronous condensers. Cal-ISO CEO Steve Berberich said on June 7 those condensers are scheduled to come online on June 26, ahead of the above-average temperatures some are already forecasting for the area during July and August.

System upgrades include additions to several substations. Additional 80 MVAR capacitors at SCE’s Santiago and Johanna substations and a 160 MVAR capacitor at the Viejo substation are operational.

Two San Diego Gas & Electric (SDG&E) substations will also see enhancements. A 230/138 kV transformer will be added to the utility’s Encina substation just south of San Onofre and a 230 kV capacitor will be added to its Penasquitos substation this summer. Other system upgrades, including the 2012 energization of the Sunrise PowerLink, have already increased SDG&E’s import capacity from 2,100 MW on June 17, 2012, to 3,350 MW today, an SDG&E spokesperson told TransmissionHub June 12.

Another project involves an upgrade to the Barre-Ellis 220-kV transmission line, which will be split from two circuits into four to provide additional redundancy. Approved in 2012, the project has been fast-tracked and is expected to be completed by June 15, a Cal-ISO spokesperson told TransmissionHub.

While primarily transmission-related, system upgrades also include the addition of three new natural gas-fired generation resources.

The Sentinel Energy Project near Desert Hot Springs, Calif., began adding 800 MW of energy to the Cal-ISO grid when it entered service in May, some three months ahead of schedule. The project is jointly owned by Competitive Power Ventures, GE Energy Financial Services, and Diamond Generating Corporation, a wholly owned subsidiary of Mitsubishi Corporation.

The Walnut Creek Energy Center in City of Industry, Calif., includes 500 MW of new generation, 10% more than the 452 MW lost by reconfiguring the Huntington Beach units. Built by a subsidiary of Edison Mission Energy, the plant entered commercial service on June 1, an Edison Mission spokesperson told TransmissionHub June 12.

NRG Energy’s 560 MW El Segundo Power Redevelopment project will replace the retired El Segundo Unit 3’s 335 MW and bring an additional 225 MW to the system. It is expected to enter service by June 30, according to the Cal-ISO spokesperson.

However, Berberich cautioned again reading too much into the value of those added megawatts because the generating units are “outside of the specific, local area that San Onofre is in, and they’re still constrained by transmission.”

Cal-ISO on June 10 published on its website a map of the southern portion of the L.A. basin and the San Diego areas, the area of greatest concern. The map also identified SDG&E’s Sunrise PowerLink and Southwest Powerlink as among the non-generation alternatives that will mitigate load-shed risk for multiple contingency events with the continuing outage of SONGS, according to Cal-ISO. Taken together, those solutions “address reliability needs without excessive reliance on load-dropping schemes,” the grid operator said.

Sponsored by

Get All the Utility Products News Delivered to Your Inbox

Subscribe to Utility Products or email newsletter today at no cost and receive the latest news and information.

 Subscribe Now


October 2015
Volume 19, Issue 9

Utility Products Topics

Transmission & Distribution
                       Vehicles & Accessories
Tools & Supplies   Safety
Line Construction & Maintenance   Test & Measurement

How to deploy mobile forms + devices to speed up field service processes & reporting

Overcoming the pain points associated with any process is much simpler and more cost effective than you think. This webinar will detail the benefits of switching to mobile forms for field data collection and reporting.
We'll examine real use cases and ROI of integrating mobile forms within a given field service process, including for work orders, inspections, checklists and proposals.
A quick AT&T Mobile Forms demo will reveal the feature rich, user-friendly nature of the solution. You'll see why it’s a must-deploy to speed up data collection, eliminate invoicing/data entry lags and auto-generate/deliver insightful reports.



Industry Company Pages

Keep up-to-date with the latest news and articles from some of the prominent utility product companies and resources.


Everlast Substation signs

Everlast safety signs and Everlast Substation signs meet all ANSI and OSHA requirements and continue to be readable for the life of the substation. When most signs fail ours shine.

Everlast pole tags

Everlast pole tags for distribution poles have been used all over the world in this great earth's worst environment's proving it is the longest lasting product to use on pole's!

Swage Bus Accessories

Swage Bus Accessories use a compression technology process called "swaging" that enables installation of aluminum bus accessories without the need of a welder.