Pacific Gas and Electric Co. (PG&E) completed a multi-year electric reliability effort to improve electric service for customers by focusing on reducing both the frequency and duration of customer outages.

In 2010, PG&E was authorized by the California Public Utilities Commission to invest $357 million to improve electric distribution system reliability through a three-year program that leveraged existing infrastructure to minimize costs and fully realize reliability benefits for customers. The program contributed to improved electrical service by focusing on three areas:

·      Installed Intelligent Switches on More than 500 Electrical Circuits: Through December 2013, more than 230,000 customer interruptions have been avoided by using this smart grid technology. In the event of an outage, instead of waiting for a crew to arrive on scene to restore circuits manually, the new devices do it automatically, often within minutes. Utility workers installed automated "intelligent" switches on almost 400 circuits last year; in total, more than 500 circuits have been enabled with this advanced "self-healing" technology.

·      Upgraded Rural Circuits: PG&E installed more than 5,000 sets of fuses and 500 line reclosers on more than 440 of the worst-performing rural circuits to isolate service interruptions and minimize their impact on customers. The installation of this equipment has resulted in a 33 percent reduction in the number of customers experiencing sustained outages from 2010 performance levels.

·      Enhanced Substations and Circuit Interconnectivity. Technicians replaced and upgraded substation equipment to improve operational flexibility and added circuit capacity to maintain or restore service when electricity needs to be rerouted in the event of an outage. These upgrades also had the benefit of handling an increase in demand during heavy loading conditions, such as hot summer days.

Sponsored by

Get All the Utility Products News Delivered to Your Inbox

Subscribe to Utility Products or email newsletter today at no cost and receive the latest news and information.

 Subscribe Now


October 2015
Volume 19, Issue 9

Utility Products Topics

Transmission & Distribution
                       Vehicles & Accessories
Tools & Supplies   Safety
Line Construction & Maintenance   Test & Measurement

How to deploy mobile forms + devices to speed up field service processes & reporting

Overcoming the pain points associated with any process is much simpler and more cost effective than you think. This webinar will detail the benefits of switching to mobile forms for field data collection and reporting.
We'll examine real use cases and ROI of integrating mobile forms within a given field service process, including for work orders, inspections, checklists and proposals.
A quick AT&T Mobile Forms demo will reveal the feature rich, user-friendly nature of the solution. You'll see why it’s a must-deploy to speed up data collection, eliminate invoicing/data entry lags and auto-generate/deliver insightful reports.



Industry Company Pages

Keep up-to-date with the latest news and articles from some of the prominent utility product companies and resources.


Everlast Substation signs

Everlast safety signs and Everlast Substation signs meet all ANSI and OSHA requirements and continue to be readable for the life of the substation. When most signs fail ours shine.

Everlast pole tags

Everlast pole tags for distribution poles have been used all over the world in this great earth's worst environment's proving it is the longest lasting product to use on pole's!

Swage Bus Accessories

Swage Bus Accessories use a compression technology process called "swaging" that enables installation of aluminum bus accessories without the need of a welder.