Siemens, Marubeni hand over power plant to Thailand utility

Sponsored by

A consortium comprising of Siemens AG, Siemens Ltd. Thailand and the Japanese partner Marubeni has completed the Wang Noi 4 combined cycle power plant in Thailand on schedule.

The owner, the state-owned utility Electricity Generating Authority of Thailand (EGAT), took the power plant into commercial operation on April 7, 2014. The natural gas fired power plant features an efficiency of over 57.3 percent with an generation capacity of 770 MW.

 

For Unit 4 of the Wang Noi power plant complex Siemens supplied the main components, comprising two model SGT5-4000F gas turbines, an SST5-5000 steam turbine, three SGen-1000A generators and the SPPA-T3000 instrumentation and control system.

The multi-shaft unit Wang Noi 4 is located in the vicinity of the Thai capital Bangkok, and is an extension of a power plant complex that is already home to three units. For unit 4, Siemens supplied the main components, comprising two model SGT5-4000F gas turbines, an SST5-5000 steam turbine, three SGen-1000A generators, and the SPPA-T3000 instrumentation & control system.

Siemens was also in charge of commissioning of Unit 4. Marubeni supplied the heat recovery steam generators, the main transformers and the cooling tower. Siemens' partner in the consortium was also responsible for the civil works and erection of the plant.

Following Wang Noi 4, the Siemens and Marubeni consortium will be completing Chana 2 CCPP, a further two single-shaft unit in the summer of 2014. Power plants with Siemens turbine generator sets, including Chon Buri IPT, Chana 1 (previously known as Songkhla), Bang Pakong 5, and Glow are making a major contribution to environmentally friendly power generation in Thailand.

Sponsored by
Most Popular Articles

CURRENT MAGAZINE ISSUE

March 2015
Volume 19, Issue 3
1503UPcover

Utility Products Topics

Transmission & Distribution
                       Vehicles & Accessories
Tools & Supplies   Safety
Line Construction & Maintenance   Test & Measurement

WEBCASTS

How to deploy mobile forms + devices to speed up field service processes & reporting

Overcoming the pain points associated with any process is much simpler and more cost effective than you think. This webinar will detail the benefits of switching to mobile forms for field data collection and reporting.
 
We'll examine real use cases and ROI of integrating mobile forms within a given field service process, including for work orders, inspections, checklists and proposals.
 
A quick AT&T Mobile Forms demo will reveal the feature rich, user-friendly nature of the solution. You'll see why it’s a must-deploy to speed up data collection, eliminate invoicing/data entry lags and auto-generate/deliver insightful reports.

UTILITY PRODUCTS BUYERS' GUIDE

POWER INDUSTRY JOBS

Industry Company Pages

Keep up-to-date with the latest news and articles from some of the prominent utility product companies and resources.

BUYER'S GUIDE PRODUCTS

Everlast pole tags

Everlast pole tags for distribution poles have been used all over the world in this great earth's worst environment's proving it is the longest lasting product to use on pole's!

Everlast Substation signs

Everlast safety signs and Everlast Substation signs meet all ANSI and OSHA requirements and continue to be readable for the life of the substation. When most signs fail ours shine.

SB01 Splice Enclosure and Accessories

AFL’s SB01 splice enclosure provides protection from all types of elements. From weather to bullets, the iron and steel construction requires no additional protective covering.