Toledo Edison is in the final stages of testing new equipment installed at two large substations that will help enhance service reliability in the area and support the expected increase in demand for electricity during the summer months.

The massive 345-kV transformers have been installed at Toledo Edison substations near Sylvania and Oregon and will be operational by June 1, 2014. Work to install these new devices began in January of 2013 and represents about a $15 million investment in service reliability.

Additionally, a multi-year project at another substation has been completed, and a new 59-mile transmission line has been energized between substations in the area. This project enhances the flexibility of the grid, allowing power to be routed around areas where storm or other damage might occur, which will help reduce the length of outages and decrease the impact on the system of severe weather events.

Toledo Edison is a unit of FirstEnergy Corp. Another FirstEnergy subsidiary, American Transmission Systems Incorporated, will own and operate the new equipment.

In addition to the new transformers, additional system work to prepare for summer demand includes aerial inspections of more than 1,000 miles of FirstEnergy transmission lines in Toledo Edison's service area. The inspections are designed to look for damaged wire, broken cross arms, failed insulators, and other hardware problems not easily detected from the ground. Any potential reliability issues identified during these inspections will be addressed promptly.

On the ground, the summer readiness inspections include using "thermovision" cameras to capture infrared images that can detect potential problems with Toledo Edison substation equipment such as transformers and capacitors. By identifying hot spots, maintenance and repairs can be conducted prior to a power outage occurring.

Other utility work being done by Toledo Edison crews includes inspecting distribution circuits, including transformers, capacitors, reclosers and lightning arrestors to ensure the equipment is operational and the lines are ready to perform efficiently when demand for electricity increases during the summer, typically due to air conditioning usage.

Tree trimming is another key to preparing the Toledo Edison system to meet the rigors of summer operations by maintaining proper clearances around electrical systems and helping to protect against tree-related outages. Toledo Edison tree contractors have trimmed more than 500 circuit miles of distribution lines since January and expect to trim another 800 miles by year end.

Sponsored by

Most Popular Articles


CURRENT MAGAZINE ISSUE

April 2014
Volume 18, Issue 4
file

Utility Products Topics

Transmission & Distribution
                       Vehicles & Accessories
Tools & Supplies   Safety
Line Construction & Maintenance   Test & Measurement

WEBCASTS

There is no current content available.

UTILITY PRODUCTS BUYERS' GUIDE

POWER INDUSTRY JOBS

Industry Company Pages

Keep up-to-date with the latest news and articles from some of the prominent utility product companies and resources.

BUYER'S GUIDE PRODUCTS

Meter Socket Converter

AE Product’s Meter Socket Converter (CNV) converts various Meter Forms to fit the desired application. 14S, 15S or 16S Socket to accept 2S Meter. Optional features available.

Service Disconnect Adapter with Electronic Meter Energizing

AEP’s Service Disconnect Adapter disconnects customer load but maintains power to the electronic meter. The meter maintains reading and communications links for AMR/AMI operations while only disabling the load side.

Meter Socket Jumpers - Perfect for Submetering Applications

AEP’s Meter Socket Jumper offers a safe and easy means of bypassing a meter socket. The Socket Jumper can be used with either Ringless or Ring style Meters.