AltaGas 195 MW run-of-river hydropower plant complete

Sponsored by

AltaGas Ltd. continues to make progress on its three Northwest run-of-river hydroelectric projects. Construction of the 195 MW Forrest Kerr facility is complete. The remaining start-up activities at Forrest Kerr will focus on commissioning the powerhouse systems and high voltage switchyard and tying in to the Northwest Transmission Line.


Construction and stringing of the Northwest Transmission Line is now complete, and commissioning is underway. AltaGas has commenced commissioning activities and expects to be generating power in July.

"With the start-up of Forrest Kerr only one month away, we are nearing completion of one of the largest projects in the 20-year history of AltaGas," said David Cornhill, Chairman and CEO of AltaGas. "The safe commissioning of Forrest Kerr is the last major step in unlocking the value it will bring to our shareholders, the Tahltan First Nation and the Province of British Columbia."

At the 16 MW Volcano Creek project, construction continues to pace two years ahead of schedule. The penstock excavation and switchyard work is underway. Assembly of the powerhouse and installation of the turbine generators is advancing. The project remains on track to be in service shortly after Forrest Kerr.

At the 66 MW McLymont Creek project, construction of the powerhouse foundation is advancing ahead of schedule and excavation of the 2,800 meter power tunnel is about 70 percent complete. The project is expected to be in service in mid-2015.

AltaGas is an energy infrastructure business with a focus on natural gas, power and regulated utilities. AltaGas creates value by acquiring, growing and optimizing its energy infrastructure, including a focus on clean energy sources.

Sponsored by

Get All the Utility Products News Delivered to Your Inbox

Subscribe to Utility Products or email newsletter today at no cost and receive the latest news and information.

 Subscribe Now


October 2015
Volume 19, Issue 9

Utility Products Topics

Transmission & Distribution
                       Vehicles & Accessories
Tools & Supplies   Safety
Line Construction & Maintenance   Test & Measurement

How to deploy mobile forms + devices to speed up field service processes & reporting

Overcoming the pain points associated with any process is much simpler and more cost effective than you think. This webinar will detail the benefits of switching to mobile forms for field data collection and reporting.
We'll examine real use cases and ROI of integrating mobile forms within a given field service process, including for work orders, inspections, checklists and proposals.
A quick AT&T Mobile Forms demo will reveal the feature rich, user-friendly nature of the solution. You'll see why it’s a must-deploy to speed up data collection, eliminate invoicing/data entry lags and auto-generate/deliver insightful reports.



Industry Company Pages

Keep up-to-date with the latest news and articles from some of the prominent utility product companies and resources.


Everlast pole tags

Everlast pole tags for distribution poles have been used all over the world in this great earth's worst environment's proving it is the longest lasting product to use on pole's!

Everlast Substation signs

Everlast safety signs and Everlast Substation signs meet all ANSI and OSHA requirements and continue to be readable for the life of the substation. When most signs fail ours shine.

Swage Bus Accessories

Swage Bus Accessories use a compression technology process called "swaging" that enables installation of aluminum bus accessories without the need of a welder.