Construction delayed on 900 MW Pennsylvania gas plant

Sponsored by

The Pennsylvania Department of Environmental Protection has granted an 18-month deadline extension under an air permit, to April 2016, for Hickory Run Energy LLC to start construction on a 900 MW power plant.

The department said in a notice in the Aug. 9 Pennsylvania Bulletin that the extension covers a 900 MW natural gas-fired combined-cycle facility in North Beaver Township, Lawrence County, according to GenerationHub.

The permit was issued on April 23, 2013. Under the permit, if the construction, modification or installation is not commenced within 18 months, or if there is more than an 18-month lapse in construction, modification or installation, a new plan approval application that meets the requirements state code needs to be submitted.

The company, which is an affiliate of LS Power, sent a June 26 letter to the department “stating that a slower than anticipated recovery in the local PJM Interconnection electrical markets resulted in the facility being unable to finance the project and commence construction prior to October 23, 2014,” said the DEP notice.

“The facility also submitted a new time table for construction which includes executing a construction contract within 6 months of the May 2015 forward capacity auction with construction commencing during the 1st quarter of 2016. The Department hereby approves an 18-month extension of commencement of construction to end on April 23, 2016.”

Sponsored by
Most Popular Articles

CURRENT MAGAZINE ISSUE

June 2015
Volume 19, Issue 6
cover

Utility Products Topics

Transmission & Distribution
                       Vehicles & Accessories
Tools & Supplies   Safety
Line Construction & Maintenance   Test & Measurement

WEBCASTS

How to deploy mobile forms + devices to speed up field service processes & reporting

Overcoming the pain points associated with any process is much simpler and more cost effective than you think. This webinar will detail the benefits of switching to mobile forms for field data collection and reporting.
 
We'll examine real use cases and ROI of integrating mobile forms within a given field service process, including for work orders, inspections, checklists and proposals.
 
A quick AT&T Mobile Forms demo will reveal the feature rich, user-friendly nature of the solution. You'll see why it’s a must-deploy to speed up data collection, eliminate invoicing/data entry lags and auto-generate/deliver insightful reports.

UTILITY PRODUCTS BUYERS' GUIDE

POWER INDUSTRY JOBS

Industry Company Pages

Keep up-to-date with the latest news and articles from some of the prominent utility product companies and resources.

BUYER'S GUIDE PRODUCTS

Everlast pole tags

Everlast pole tags for distribution poles have been used all over the world in this great earth's worst environment's proving it is the longest lasting product to use on pole's!

Everlast Substation signs

Everlast safety signs and Everlast Substation signs meet all ANSI and OSHA requirements and continue to be readable for the life of the substation. When most signs fail ours shine.

SB01 Splice Enclosure and Accessories

AFL’s SB01 splice enclosure provides protection from all types of elements. From weather to bullets, the iron and steel construction requires no additional protective covering.