PJM studies impact of Maryland biomass/solar power project

A PJM Interconnection study on the project, dated February 2015, added that the facility will be located in Pocomoke City, Maryland

Content Dam Elp Online Articles 2015 January Pjm Interconnection Elp

Chesapeake Renewable Energy LLC has proposed a 19.9 MW MFO (15.9 MWC) generating facility consisting of a 13.5 MW biomass-fired steam boiler and turbine/generator and a 6.4 MW solar power array, according to GenerationHub.

A PJM Interconnection study on the project, dated February 2015, added that the facility will be located in Pocomoke City, Maryland. PJM studied this project, under queue No. AA1-107, as a 19.9 MW injection into the Delmarva Power and Light (DPL) system at a tap of the Costen-Pocomoke 138 kV circuit and evaluated it for compliance with reliability criteria for summer peak conditions in 2018. The planned project in-service date, as stated in Attachment N, is Dec. 1, 2016.

The intent of this combined feasibility/system impact study is to determine a plan, with approximate cost and construction time estimates, to connect the subject generation interconnection project to the PJM network at a location specified by the Chesapeake Renewable Energy. This study is a mid-point in the queue process at PJM, which culiminates with the signing of an interconnection service agreement. The project entered the queue in October 2014.