Honeywell, Tinker Air Force Base launch energy efficiency project

The project will help Tinker meet the mandated 30 percent energy reduction goal defined by Presidential Executive Order 13514

Minneapolis, October 30, 2012 — Honeywell announced an $80.6-million energy efficiency project for the U.S. Air Force that will improve operations and cut utility costs at Tinker Air Force Base near Oklahoma City.

The project is the Air Force's largest domestic energy retrofit funded through guaranteed savings to date. And, combined with previous Honeywell-led improvements and other on-base initiatives, it will help Tinker meet the mandated 30 percent energy reduction goal defined by Presidential Executive Order 13514. It should also remove Tinker from atop the list of the most energy-intensive Air Force bases.

The upgrades are expected to save $6.4 million the first year after the work is complete and more than $170 million over 20 years, guaranteed by Honeywell through an energy savings performance contract.

The Air Force plans to use the reduction in utility and operating expenses to pay for the project and ongoing maintenance, which Honeywell will also provide. As a result, Tinker AFB should not have to increase its budgets or request additional taxpayer dollars.

The improvements will have an impact on energy and water consumption as well, trimming the use of natural gas by almost 27 percent and fresh water by about 20 million gallons per year. Annual carbon dioxide emissions are also estimated to decrease by more than 60 million pounds, equivalent to removing 6,100 cars from the road.

In addition, the project will help create and sustain local jobs, with more than 500 Honeywell workers and supporting tradespeople expected on site during peak construction.

Under the contract, Honeywell will oversee hundreds of energy- and water-saving upgrades, and will help maintain and repair the equipment it installs. The company's technicians will decommission three central steam plants and downsize a fourth, removing 56 buildings from the base's steam heat grid.

The plants will be replaced by high-efficiency heating equipment at each building, which requires putting in more than four miles of natural gas piping, about 130 packaged hot-water and steam boilers, and a variety of infrared and direct-fired gas heaters.

Honeywell will operate the new boilers and manage the water treatment program for the equipment. And it will enhance 15 other facilities that will remain on the steam grid. Overall, the company will leverage its project management experience to help complete the work while minimizing the impact on day-to-day activity at Tinker AFB.

To measure and verify the energy savings, Honeywell will install an advanced metering system, which will include submeters from E-Mon, its subsidiary. Metering data will be tied into Honeywell Energy Manager and displayed on an energy dashboard, which will provide a granular view of how and where natural gas and electricity are being consumed. Tinker AFB will also use its existing Honeywell Enterprise Buildings Integrator for overall control of heating, cooling and metering equipment.

The construction phase of the project is expected to be complete in 2015.