Minnesota approves Xcel Energy's wind power plan

Minnesota Public Utilities Commission approves plan for 1,550 MW of low-cost wind energy

Content Dam Elp Online Articles 2017 06 Wind Power 1 Elp

The Minnesota Public Utilities Commission approved Xcel Energy’s plan for the largest expansion of wind energy in the Upper Midwest. The North Dakota Public Service Commission will review the plan later this year.

The new wind power projects will save Xcel Energy customers billions of dollars in fuel and other costs, as compared to the costs of other energy sources. Seven new wind farms are slated to be built in Iowa, Minnesota, North Dakota, and South Dakota and will be operational by the end of 2020. The projects will provide enough energy to power more than 800,000 homes, increasing Xcel Energy’s regional wind output by about 70 percent.

“We’re investing in low-cost wind energy to provide the benefits of clean, affordable energy directly to our customers,” said Chris Clark, president, Xcel Energy-Minnesota. “These projects deliver on our plan to keep energy costs low while also reducing carbon emissions by more than 60 percent in the coming decades.”

With these new wind farms, Xcel Energy is locking in low-cost, carbon-free energy. As no fuel is needed for wind farms, the cost of electricity from the wind farms is not affected by fuel price spikes. Customers receive the benefit of low, stable electricity prices from these wind farms for the 25-year life of the projects.

“Our strategy delivers the long-term value our customers tell us they want,” said Clark. “These projects give our customers both lower bills over the long term and predictable prices, in addition to a cleaner energy mix.”

Xcel Energy will own 1,150 megawatts of the new wind energy; the remaining 400 megawatts will be sold to the company under long-term power purchase agreements.

Project details

· Freeborn Wind Energy, a 200 MW project located in Freeborn County, Minnesota, and Worth and Mitchell Counties, Iowa.

· Foxtail Wind, a 150 MW project located in Dickey County, North Dakota.

· Blazing Star 1, a 200 MW project located in Lincoln County, Minnesota.

· Blazing Star 2, a 200 MW project located in Lincoln County, Minnesota.

· Crowned Ridge Wind Project, a 600 MW project located in Codington County, South Dakota.

· Lake Benton Wind Project, a 100 MW project in Pipestone County, Minnesota.

· Clean Energy 1, a 100 MW project in Morton and Mercer counties, North Dakota.

All projects are expected to be completed by the end of 2020, qualifying them for 100 percent Production Tax Credit.