Improved feeders had 39 percent fewer outages and 42 percent shorter outages

Improved feeders had 39 percent fewer outages and 42 percent shorter outages

Customers are seeing improvements in service reliability as Pepco continues its reliability improvement work. From 2011 to 2012, outages on feeders the utility worked on as part of its improvement plan decreased day to day by 39 percent, and on those that did have outages were 42 percent shorter.

Pepco began a strategic initiative in September 2010 to improve reliability including trimming trees and replacing underground cable and power lines that span thousands of miles.

Since the start in Sept. 2010 thru Jan. 31, 2013, Pepco has:

· Trimmed more than 4,850 miles of trees along power lines in Maryland and about 850 miles in the District of Columbia. Pepco plans to trim another 1,225 miles in Maryland and the District between now and the end of the year.

· Renewed or replaced more than 650 miles of neighborhood underground electric cable in Maryland, 58 miles in the District and plans to do the same for another 200 miles between now and the end of 2013.

· Improved the service of feeder lines that bring power into neighborhoods with the poorest reliability by upgrading more than 115 distribution feeders in Maryland, 66 feeders in the District of Columbia and plans to complete work on about 100 more this year in the region.

· The utility has improved its customer care center, where it doubled the number of representatives who take customer calls to 80 and more than doubled the phone lines — from 300 to 644.